a contractor estimates that he can paint a house in 5 days using 6 men. if he actually uses 5 men for the job, how many days will they take to paint the house?

Respuesta :

Einstein08 Einstein08
  • 01-09-2018
it will take 4 days to paint the house with 5 men
Answer Link
tramserran
tramserran tramserran
  • 01-09-2018

1 house = 6 men x 5 days  = 30 man days

Need 30 man days with only 5 men: 30x = 5 men   →  x = 6

It will take 6 days for 5 men to complete the job.

Answer: 6 days


Answer Link

Otras preguntas

Which was not a result of poverty in America's urban centers? A. overcrowded and crime-ridden inner cities B. peaceful integration of once-segregated neighborho
Subtract 4 ounces from 5 pounds. 3 lb., 12 oz. 5 lb., 6 oz. 4 lb. 12 oz. 3 lb., 8 oz.
Help me with 1,2,3 pls thx
3 examples of proteins in living organisms
Which rhetorical device is used in this statement from Dr. Martin Luther King Jr.’s speech “I Have a Dream”? I have a dream that one day this nation will rise u
what's the value of of x
Which of the following is not a power of the president?
Which of the following is NOT an example of the ways the media serves as a linkage institution for government? a)covering the activities of government b)reporti
A sail on a sailboat is a triangle with two sides perpendicular and each side is a different length. What are the two terms that could be used to describe the s
Choose the correct product of (2x − 4)2. 4x2 − 16 4x2 − 16x + 16 4x2 + 16 4x2 + 16x + 16